Subdivision and Land Development Fees & Charges

Resource Management Fees and Charges approved for ...

Resource Management

Resource Management Fees and Charges approved for 1 July 2023 to 30 June 2024.

All fees and charges are inclusive of GST (except as noted *).

Resource Management Fee (incl GST)
Note: Pursuant to Section 36, 36(1) and 36(3) of the Resource Management Act 1991, Council may require the personwho is liable to pay one or more of the below charges, to also pay an additional charge to recover actual and reasonable costs in respect of the matter concerned.
Note: Note: These fees relate to the minimum charge only payable prior to assessing the application. Consents will not be processed until payment has cleared. Actual fee payable includes the cost of time taken to process each application, memorandum, consent, notice, certificate or schedule, the cost of disbursements, plus any inspections required. Should the application be withdrawn prior to a deposit being issued, the minimum fee is non-refundable
Note: Extra charges will be applicable for development levies. These will be assessed on a case by case basis. Please contact Council for exact costs.
Land Use
Deemed Permitted Boundary Activity (s87AAB)$400.00 
Controlled Activity (Plus actual and reasonable costs)*$1,000.00 
Restricted Discretionary Activity (Plus actual and reasonable costs*$1,500.00 
Discretionary Activity (Plus actual and reasonable costs)*$2,000.00 
Non-Complying (Plus actual and reasonable costs)*$2,500.00 
Variation of Conditions of Consents (s127) (Plus actual and reasonable costs)**$1,500.00 
Limited Notified Applications (Minimum Fee) (Plus actual and reasonable costs)$5,000.00 
Public Notified Applications (Minimum Fee) (Plus actual and reasonable costs)$10,000.00 
Extension of Time application (s125) (Plus actual and reasonable costs)*$1,000.00 
Subdivisions
Controlled (Plus actual and reasonable costs)*$1,500.00 
Restricted Discretionary (Plus actual and reasonable costs)$2,000.00 
Discretionary (Plus actual and reasonable costs)*$2,500.00 
Non-Complying (Plus actual and reasonable costs)$3,500.00 
Limited Notified Applications (Minimum Fee) (Plus actual and reasonable costs)$5,000.00 
Public Notified Applications (Minimum Fee) (Plus actual and reasonable costs)$10,000.00 
Variation of Conditions of Consent (s127) (Plus actual and reasonable costs)$1,500.00 
Extension of Time Application (s125) (Plus actual and reasonable costs)$1,000.00 
Subdivision Compliance Fee (section 223 and/or 224 Resource Management Act 1991) (1 - 4 lots) (Plus actual and reasonable costs)$650.00 
Subdivison Compliance Fee (section 223 and/or 224 Resource Management Act 1991) -( 5 or more lots) (Plus actual and reasonable costs)$1,500.00 
Certification Fee (consent notices, demalgamation certiication, cancellation of easement, esplanade etc.) Per Certificate$250.00 
Engineering approval for section 224 (1-4 lots) (Plus actual and reasonable costs)$500.00 
Engineering approval for section 224 (5 or more lots) (Plus actual and reasonable costs)*$800.00 
ROW application (S348 LGA)*$700.00 
Property file creation (Payable at 223/224 application) Per new lot$80.00 
Miscellaneous
Certificate of Compliance (s139)(Minimum fee) (Plus actual and reasonable costs)*$1,000.00 
Certificate of Existing Use Rights (s139A Resource Management Act 1991) Plus actual and reasonable costs$1,000.00 
Designation/Notice of Requirement (Plus actual and reasonable costs)$3,000.00 
Outline Plan of Works (s176A) (Plus actual and reasonable costs)$1,500.00 
Outline Plan Waiver$500.00 
Alteration to Designation (Plus actual and reasonable costs)$1,500.00 
Chargeout rates per hour
Administration$150.00 
Planner$180.00 
Senior Planner, 3 Waters and Land Transport$195.00 
Manager, Team Leader $210.00 
EngineersActual and reasonable costs* 
Technical Report Peer ReviewActual and reasonable costs* 
Administrative Charges
Bond Administration Fee$200.00 
Supply of documentsPhotocopying Costs 
District Plan Charges
Private District Plan Change (Deposit)$15,000.00 
Designations and heritage orders (New and alterations) (Deposit)$1,500.00 
District Plan (including Planning Maps) Electronic$50.00 
District Plan (including Planning Maps) HardcopyActual and reasonable costs 
Compliance and Monitoring
Inspection Fee - Zone 1$230.00 
Inspection Fee - Zone 2$240.00 
Inspection Fee - Zone 3$265.00 
Inspection Fee - Zone 4$295.00 
Inspection Fee - Outside Zone 4$335.00 
Travel Costs (per km)$1.20 
Sale of Liquor Certificate (RMA)$140.00 
Objection of RMA decisions (Section 357) (Deposit)$1000 lodgement fee plus actual and reasonable charges* 

Development Contributions Fee (incl GST)
 
Districtwide$1,621.50 
Waipukurau$28,522.30 
Waipawa$28,522.30 
Otane$28,522.30 
Takapau$8,676.75 
Porangahau$23,259.90 

Loading...

Central Hawke's Bay District Council - Copyright © 2024 Central Hawke's Bay District Council

Disclaimers and Copyright
While every endeavour has been taken by the Central Hawke's Bay District Council to ensure that the information on this website is accurate and up to date, Central Hawke's Bay District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Central Hawke's Bay District Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Central Hawke's Bay District Council - / +64 6 857 8060 / customerservice@chbdc.govt.nz