CHB Water Renewals

CHB Water Renewals

CHB Water Renewals

You can follow the specific project updates by visiting the drop down for individual projects below.

Update - 09 April 2019

Council is pleased to announce the award of this contract for the project to upgrade approx 925m of water main in Mackie and Mclean Terrace to Fulton Hogan Ltd. Works are planned to commence Monday 15th April 2019 and run through to mid August 2019.

Update - 05 April 2019

Council is currently finalising contract details with our preferred supplier for the Mackie/ Mclean project. 

Update - 21 February 2019

The project for Mackie Street and Mclean Terrace, Waipukurau is currently out for tender and in the open market via GETs.

Update - 21 January 2019

Council has identified our next set of water renewals and is currently finalising the design to tender for the physical works shortly.

This work will see a section of AC water main replaced along Mackie and McLean street in Waipukurau. The works are planned to be completed by 30 June 2019.

Update - 6 November 2018

Each year council has defined budget as outlined in our LTP to replace water network that is modelled for replacement as per our asset management plans, and confirmed through investigation and scoping.

  • Council has one renewal project due to commence in Dec 2018 in Porritt Place, Waipukurau.
  • Council has identified 2 - 3 areas for replacement in the 2018/19 cycle due by 30 June 2019.

CHB Water Renewals: Mackie St & McLean Tce, Waipukurau

Update: 11 July 2019

Both new water mains are now live and connected to the Council water network with all households connected to the new pipes with new laterals and water toby’s. Fulton Hogan are working with their sub-contractors to rehabilitate the footpaths and road surfaces with work currently underway in Mackie Street to complete the road surface now that the footpaths are completed.

Next week the last shutdown will take place along Porangahau Road to allow the last connection onto the town network to take place.

1005 Waipukurau Water Improvements Mackie St 20190625 6

Update: 27 June 2019

Installation of the Mackie Street section of new water main and service laterals has been completed with the last connection of the new pipe network to the Council Water Network on Tuesday 25 June. All the water connections along Mackie Street are now been supplied off the new Water Network that Fulton Hogan have installed over the past 2 months.

Work is progressing well in McLean Terrace with the remaining new water main pipes completed, and half of the new water laterals to properties completed. Once the last few have been completed this week the contractor plans the carry out cleaning and testing of the new network next week which then allow the new network to be connected into the existing town network.

Photo below of new valve arrangement installed on the Mackie Street Section.

1005 Waipukurau Water Improvements Mackie St 20190625 6

Update: 13 June 2019

The new water main on Mackie Street passed testing late last week, and is now ready for connecting into Council’s Water Network. The connection into the network is programmed to start on Tuesday 18th June at the Freyberg Tce end first, followed by the McLean Terrace connection later that week, After the new water main is live, the contractor will then commence changing over all house connections to the new water network. The last piece of the work for Mackie Street is to connect the new water main pipe onto the existing water network in McCarthy Terrace.

The contractor will then start installing the new house service connections for McLean Terrace in preparation for testing on the McLean Terrace Water Main in the coming weeks.

We expect the project to be complete by mid July 2019, approximately 3 weeks ahead of originally planned schedule.

1005 Mackie St Water 20190612 4

Update: 29 May 2019

Work has progressed well over the past two weeks with all but 20m of the new PE Watermain installed in both Mackie Street and McLean Terrace.

Fulton Hogan are currently working on installation of the new service laterals along Mackie Street with the aim to have these completed by the end of this week.

This will allow for testing and cleaning of the new network in Mackie Street to be undertaken week starting 3rd June 2019, prior to the changeover to the new network which is planned for week starting 11th June 2019 subject to progress and confirmation of the testing.

Once Mackie Street is changed over to the new water network, Fulton Hogan will then commence with the McLean Terrace water laterals.

McLean Tce Water Pipe

Update: 15 May 2019

Work has progressed well over the past week and a half with the new water main and ridermain water pipe installed in Mackie Street.

Fulton Hogan’s sub-contractor Xtreme Contracting have directionally drilled all the new pipe which has meant a quick installation process with less road trench reinstatement work.

Over the coming weeks the water lateral to each property will be installed onto the new water main, cleaning and testing of the new pipes will then be carried out before each property is connected to the new water network.

Fulton Hogan are working with Council to minimise any disruption during the changeover phase to the new water network by having the old and new water mains live together.

Work has commenced in McLean Terrace with work continuing over the coming two weeks installing the new water pipes.

DN125 Main on Rollers Mackie Street

Update: 09 April 2019

Central Hawkes Bay District Council is pleased to advise we have awarded a contract to Fulton Hogan Ltd for the project to renew the existing water supply line and lateral connections in Mackie Street and McLean Terrace, Waipukurau.

We propose to install approx. 305m of 125 PE water main on the western side along Mackie Street and 26 service lateral connections with 270m of 63mm PE rider main down the eastern side. McLean Terrace will see 224m of 125mm PE water main and 16 service connections with 139m of 63mm rider main of 63mm OD PE installed along the southern side.

The project is planned to commence on the 15th April 2019 and run through to mid-August 2019. Hours of work will generally be between 7:30am and 6:00pm on the weekdays and 7:00am to 5:00pm on a Saturday.

MAckie and McLean pg 1

 

MAckie and McLean pg 2

Update: 05 April 2019

Council underwent a robust and competitive tendering process and is finalising a contract. All going to plan council expects work to commence at the end of April 2019 through the end of July 2019.

The works as outlined below, involve approx. 925m of water mains replacement.

Map of Works

Update: 23 January 2019

Council is currently finalising the design for this project which will involve renewing the AC water main in Mackie and Mclean Street, Waipukurau.

CHB Water Renewals: Porritt Place, Waipukurau

Update: 05 April 2019

Council is pleased to advise that all works are complete and asbuilts are currently being updated into our GIS system.

Update: 21 January 2019

Council is pleased to provide an update that the project is progressing well and as planned, all water network works are complete, and only final road carriageway reinstatement remains. Council expects this to be complete by the end of Jan 2019. 

Thank you all for your patience whilst we have undertaken these works.

90 Project Update 21 Jan 2019

Update: 20 December 2018

Website Project Progress UpdatePorritt PlaceCHB Water Renewal Project

Website Project Progress Update Porritt Place CHB Water Renewal Project2

 

Update: 28 November 2018

Porrit Place Big Water Story

 Porrit Place Big Water Story 2

Loading...

Central Hawke's Bay District Council - Copyright © 2019 Central Hawke's Bay District Council

Disclaimers and Copyright
While every endeavour has been taken by the Central Hawke's Bay District Council to ensure that the information on this website is accurate and up to date, Central Hawke's Bay District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Central Hawke's Bay District Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.