skip to main content

Waipukurau Water SH2 Bore Upgrade

Waipukurau Water SH2 Bore Upgrade

Waipukurau Water SH2 Borefield Upgrade

Update - 18 Sep 2019

Bore drilling is to commence on site from 30 Sep 2019 for a period of 3 weeks to replace two bores, works is also expected to take place in mid Oct 2019 by Centralines to upgrade the current overhead 200kva transformer to a pad mounted 500 kva transformer.

Update - 23 Aug 2019

A new Pump for Bore B is on order, and the works required to replace Bore D and E is scheduled for Sep 2019.

The electrical design and shed extension is under review.

The project continues to progress with its many facets, and council is working towards a late Dec 2019 completion.

Update - 25 July 2019

Council has awarded a contract to Max Tarr Ltd in conjunction with WSP-Opus to deliver this key project.

Works and planning are currently underway, with the following key items in progress;

- Camera assessments of the bores

- Relocation and upgrade of the in-situ transformer with Centralines

- Building extension to house the upgraded controls

- Fencing changes

Physical works is expected to commence onsite in Aug 2019, trenching in new pipelines, extending the building housing the controls, and general civil works.

Update - 21 June 2019

This project has progressed to contract negotiations, and Council expects to have awarded a contract and finalised a programme by early July 2019.

This week, did mark a milestone for works to progress with the re-installation of 'pump A' , this adds resilience back to the borefield and the project team can now focus, on finalising the works to upgrade Bores B, C, D and E.

Council still expects works to take approx 4 months, and be completed by December 2019.

Update - 05 April 2019

This project is currently under tender and Council expect to have awarded a contract to our preferred supplier in May 2019.

There have been some delays to the works programme due to the unexpected failure of the main Pump 'A' at this borefield. Council expects works to take approx 4 months, and be completed by December 2019.

On completion, there will be four lineshaft pumps including Pump 'A' with the ability to variably pump water to the Pukeora reservoir.

Update - 18 January 2019

The design aspect of this project is progressing well, council is currently finalising the design and pipe layout and plans to tender this work out in Feb/ March 2019.

Draft Design SH2 Bore Upgrade Layout

Update - 6 November 2018

Council has a project to upgrade the bores that supply water to the Pukeora reservoir and the township of Waipukurau. A number of the pumps are nearing end of life and require replacement.

Council is also taking the opportunity to upgrade the electrical control system and install flow and turbidity meters on all bores to assist with the maintenance and drinking water standard (DWS) compliance.

Council is currently finalising the detailed design, and is aiming to tender the works out in early 2019 for physical completion by 30 June 2019.

Further updates will be provided as the project progresses.

Loading...

Central Hawke's Bay District Council - Copyright © 2019 Central Hawke's Bay District Council

Disclaimers and Copyright
While every endeavour has been taken by the Central Hawke's Bay District Council to ensure that the information on this website is accurate and up to date, Central Hawke's Bay District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Central Hawke's Bay District Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Central Hawke's Bay District Council - / +64 6 857 8060 / customerservice@chbdc.govt.nz