skip to main content

Waipawa Trunk Sewer Main RenewalTe whakahoutanga o te ara kawe para matua i Waipawa

Waipawa Trunk Sewer Main Renewal

Waipawa Trunk Sewer Main Renewal

Update - 18 November 2019

Lining is well underway, last week saw over 800mtrs of liner installed – just over a third of the full 2200mtrs planned, this week we continue to line between Guy and Shanly street in Waipawa.

Communication continues with properties and residents affected, and we are on track to have this all but wrapped up by the Xmas break! With a small piece of work at the pump station to be completed in Jan/ Feb 2020.

IMG 2193

Update - 11 November 2019

This week we start the renewal of the trunk sewer main that was installed in 1910. 

Over the last few weeks we have been cleaning the main and getting good CCTV footage of the internal walls, along with confirming all laterals and connections, we have also relocated a manhole and installed a new manhole.

We are now ready to line the main with a new pipeline, a resin saturated fabric liner is installed into the main, unfolded, and then cured in place. Once started, the work has to continue to ensure the line cures, each shot is expected to take two x 24 hour days.

We expect all lining works to be complete by early December 2019, and the remaining works to be complete by the Christmas break approx. 20 December 2019. There will be some noise associated with machinery, and some smell associated with the curing of the liner.

Update - 01 November 2019

During the cleaning process, we have come across a significant blockage in the pipeline, that is also complicated by a long stretch of pipeline between manholes, approx. 320mtrs. 

To assist with removing the blockage, and assisting with maintenance moving forward - we have installed an additional manhole.

IMG 2189

Update - 29 October 2019

Works is progressing well, as we prepare for lining, we are busy relocating a manhole that had structural issues.

IMG 0116

Update - 14 October 2019

The project officially commences today, and signs are going up on the corner of some of the routes to advise the local residents and road users what the work is and why the vehicles may be on the roads.

IMG 0082

 

Update - 04 October 2019

Council recently held a community evening on the project, which was well received, and through and informative questions were asked by the group.

Presentations were given by Council, The Property Group (landowner relations), and Pipeworks/ Higgins (contractors undertaking the work).

We now continue to plan for works to start on 14 October 2019.

Update - 23 September 2019

A flyer on the community information session on Tuesday 1 October 2019 is being delivered to residents this week.

Update - 18 September 2019

Council has made good progress with the affected stakeholders and expects to commence work early October 2019. 

Prior to works commencing, Council, our contractor - Pipeworks, and The Property Group, who have lead the stakeholder engagement will be holding an open evening community session to provide a presentation and Q&A session on the project. 

This is planned for Tues 1st October 2019 from 7pm-9pm in Council Chambers.

Specific communications will be released on this next week.

Update - 30th August 2019

A further letter drop was released to landowners and affected parties this week. 

The Waipawa Trunk Sewer Main Renewal project consists of the sewer line rehabilitation for 2.2 km of earthenware sewer east of the Waipawa town centre. The sewer main is largely located within private property with multiple defective joints that allow groundwater infiltration and root ingress. PipeWorks proposes to rehabilitate the existing 375 mm diameter pipe using cured in place pipe (CIPP) inducted by hot water. 

Council and its contractor PipeWorks will aim to minimise any disturbance to you caused by this work however, it is important that you are aware of the type of activities that will occur during the works. These are outlined as follows.

1. Noise: During the relining works, PipeWorks need to run various items of construction plants. Including air compressors, generators, boiler and other items powered by diesel engines.

2. Traffic: Some construction vehicles will be required to park on the side of the road, however PipeWorks expect this to cause minimal disturbance to residence and road users. Some vehicles or workers may require access to your property in order to access existing manholes within the pipeline. Where this is the case, you will be contacted firstly and well in advance.

 3. Smell: The liner is impregnated with polyester resin. There will be some smell present during installation period. PipeWorks expect this not to be noticeable beyond 10 meters. For properties close to the relining works, as they progress along the pipeline alignment, sensible actions that can mitigate any smell are those such as closing the windows to your house.

Update - 25 July 2019

Planning is ongoing on this project, council is currently working with landowners to gain access to the pump station for the upgrades planned, and secure easements for power and sewer lines.

In addition, Council is working with Centralines to deliver a transformer relocation and power upgrade to the McGreevy Street pump station.

Update - 21 June 2019

This week marked an important milestone for this project where the contract was officially signed and awarded to Pipeworks Ltd, to be supported by Higgins.

This project is to renew 2200m of the 375mm gravity sewer main that runs from the McGreevy Street pump station all the way through the back of properties to the Waipawa Wastewater treatment pond (WWTP), this is a key project as part of the wider Waipawa WWTP improvements as well as improving infiltration and inflow into the network, whilst providing a better level of service.

A pump station upgrade at McGreevy Street will also form a part of this project – work is expected to commence in Sep 2019 and be complete by Dec 2019, over the next few months, Council will concentrate on ensuring all landowners are across the works proposed prior to commencement.

Website Project Overview with Properties 21 June 2019

Update - 05 April 2019

The project is currently in the open market under tender, council is also currently working with affected landowners to prepare for the access required and the pump station upgrade.

We expect to have awarded a contractor by June 2019 and aim to complete all works by December 2019. 

Drawing 2Drawing 1

Update - 27 March 2019

The linked letter was dropped to landowners that may be affected by the works this week.

Please contact council should you have any questions or concerns.

Update - February 2019

Following approval of the option in December 2018, GHD Ltd proceeded to develop a concept design to;

 Mitigate root intrusion & other factors that impact operational performance
 Reduce infiltration
 Maintain Dry Weather Flow capacity
 Improve Peak Wet Weather Flow capacity to provide conveyance for 1-in-2 year Storm (current), at 187 l/s.

Update - 20 December 2018

An option assessment was undertaken by GHD and CHBDC to better understand the upgrade options we had available for this pipeline.

From this option assessment, a workshop was held with Council and a preferred option identified.

OptionsPref Options

Update - 6 November 2018

Following a tender and evaluation process, Council has awarded the design component of this project to GHD, and will start the design and risk review component this month.

This will involve reviewing CCTV, scoping and confirming the best renewal technique for this project. This will be reliant on the structure of the pipe. Due to the location of the pipe, a fair amount of stakeholder communication will take place prior to any works starting.

Council plans to start physical works following a tender phase in May 2019 allowing for a 5 month construction window and aiming to complete works by November 2019.

Further updates will be provided as this project progresses.

Update - 29th August 2018

This project involves the cleaning and relining of the 375mm trunk sewer main that runs from McGreevy Street to Guy Street, and then again from Shanly Street to Johnson Street in Waipawa. This work will proactively prevent further tree root intrusion, and addresses the infiltration of ground water into the waste water system.

Project OverviewCatchment Flows

The Waipawa Trunk Sewer Main Renewal project consists of the sewer line rehabilitation for 2.2 km of earthenware sewer east of the Waipawa town centre. The sewer main is largely located within private property with multiple defective joints that allow groundwater infiltration and root ingress. PipeWorks proposes to rehabilitate the existing 375 mm diameter pipe using cured in place pipe (CIPP) inducted by hot water. PipeWorks believe that the replacement of the 375mm concrete capped sections of pipe can be reinstated using our normal CIPP process. 

 

Loading...

Central Hawke's Bay District Council - Copyright © 2019 Central Hawke's Bay District Council

Disclaimers and Copyright
While every endeavour has been taken by the Central Hawke's Bay District Council to ensure that the information on this website is accurate and up to date, Central Hawke's Bay District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Central Hawke's Bay District Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Central Hawke's Bay District Council - / +64 6 857 8060 / customerservice@chbdc.govt.nz