skip to main content

Leachate to LandTuhinga o mua

Leachate to Land

Leachate to Land Irrigation Project

Central Hawkes Bay District Council (CHBDC) has commenced a project to irrigate the leachate produced by the landfill back onto a capped and completed area of the landfill.

Update - 04 October 2019

We are now investigating a borrow site at the back of the landfill that will be used as final cover to shape the capped area on the landfill where the leachate will be irrigated onto. This is important in getting the right type of fill to ensure the permeability is correct for irrigation.

20191004 130534

Update - 03 October 2019

The pond has largely taken shape and is now being prepared for lining.

20191004 124444

Update - 01 October 2019

The team has now shifted to excavating the new trench for the stormwater line that will provide the subsoil drainage.

Trench 01 Oct

Update - 26 September 2019

The pond is taking shape and Stringfellows are working through creating the batters and gradients in preparation for inspection.

20190924 091126

Update - 24 September 2019

Stringfellows are currently excavating around the old leachate pond and continuing to create the new pond shape.

20190924 090325

Update - 20 September 2019

Earthworks on the new leachate pond is progressing well as our contractor Stringfellows currently forms the new pond shape.

20190920 102219

Update - 16 September 2019

Work is progressing well - glass has been shifted to a new bunker, and the team now start earthworks and creating the leachate pond.

20190913 095655

Update - 02 September 2019

Last week council endorsed a report to approve the additional budget required to complete this project, this week the start-up meeting takes place, and the contractor starts establishing site, the project involves shifting all the glass stored at the landfill away from the project site to a purpose built bunker (this glass is stored to be used in future as basecourse for any new cells), a large leachate pond is to be created, along with a new pump station and pipeline through to an irrigation area where new irrigation pods will be installed to irrigate the leachate onto a capped cell area of approx. 1.2ha.

Leachate Project Site

Update - 25 July 2019

Council has completed a robust procurement process and has identified a preferred supplier for this project.

Council now works to seek the relevant approvals, and is in the planning stages with the contractor and the landfill operations contractor to progress this project.

Works are expected to commence in late Aug 2019.

Update - 05 April 2019

A resource consent has been submitted to Hawke's Bay Regional Council to amend the current resource consent conditions to allow us to irrigate the leachate back onto the landfill. 

Following granting of consent conditions, Council plans to take this project to the market to identify a suitable partner to undertake the proposed works.

Below is an overview of the proposed irrigation area.

Leachate Irrigation Zone

Update - 21 February 2019

Three options regarding storage for the leachate project have been presented, CHBDC have reviewed the options and agreed to proceed with an option to increase the pond storage currently in-situ on the landfill. At present CHBDC are preparing a resource consent application to allow for this change in consent on how we manage the leachate. CHBDC expect to have lodged the consent with HBRC by mid March 2019.

Update - 14 January 2019

CHBDC commissioned a survey of the landfill to help better understand the topographic and levels to progress improvements at the landfill and inform the leachate project requirements, in particular the surface area required to irrigate the leachate on. Below is a snapshot of the survey image.

Landfill Survey Graphic

 

Update - 07 January 2019

Council has re-commenced a project that was conceived in 2011, to eliminate tankering the leachate produced at the landfill to the wastewater treatment pond in Waipukurau, and to instead create a circular system where the leachate is captured and irrigated back onto a completed area/ phase of the landfill.

This holds benefit for the wastewater treatment process - as leachate can be high in ammonia.

The project once completed is expected to reduce operational costs as well as better our environmental and carbon footprint through reduced emissions from tankering the leachate numerous times a day.

The project is in the early stages, design is to be completed and then a contractor procured to deliver this project. 

Council hopes to have a system up and running in early 2020.

Loading...

Central Hawke's Bay District Council - Copyright © 2019 Central Hawke's Bay District Council

Disclaimers and Copyright
While every endeavour has been taken by the Central Hawke's Bay District Council to ensure that the information on this website is accurate and up to date, Central Hawke's Bay District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Central Hawke's Bay District Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Central Hawke's Bay District Council - / +64 6 857 8060 / customerservice@chbdc.govt.nz